Project Summary
SYS was commissioned by Malaysia Marine and Heavy Engineering Sdn Bhd (MMHE) to undertake dredging works for the redevelopment of deepwater facilities at MMHE Quay No. 6 in Pasir Gudang, Johor. The primary objective was to excavate and remove soil and rock from the seabed to create a berthing pocket suitable for load-out barges and vessels up to -10 meters Chart Datum (CD).
Given the concurrent operations at the shipyard, SYS had to ensure uninterrupted access to the site for ongoing activities, including load-out and fabrication. The dredging involved removing a total of 240,477 cubic meters of material, with rock samples tested and determined to require blasting due to their hardness.
Project Details
- Dredged volume: 240,477m³ (up to -10m CD)
- Dredged materials get harder as depth increases. Rock sample was taken to Geolab laboratory for hardness testing and the result falls under the rock blasting zone
Dredging Works for Redevelopment for Deepwater Facilities at MMHE Quay No. 6, Pasir Gudang, Johor
Malaysia Marine and Heavy Engineering Sdn Bhd (MMHE)
Malaysia Marine and Heavy Engineering Sdn Bhd
Dredging & Reclamation
Pasir Gudang, Johor
April 2008 -
October 2009
RM 17,500,000
related
projects
Discover the breadth of our expertise through our diverse range of projects and joint ventures
Useful Links
Plant & Equipments
Contact Us
Headquarters
Unit 2001, Level 20, Tower 1, Faber Towers, Jalan Desa Bahagia, Taman Desa, 58100 Kuala Lumpur, MALAYSIA
Phone: +603 7980 6266
Fax: +603 7980 5199
Plant & Workshop
Lot 2964, 2 ½ Miles, Jalan Minyak Beku, 83000 Batu Pahat, Johor, MALAYSIA
Phone: +607 434 2563
© 2024 See Yong & Son Construction Sdn Bhd | All Rights Reserved.