pulau indah power plant

P214 | Marine Structures

Project Summary

Awarded to SYS on 18th August 2021 and commenced on 1st October 2021, this project involves the construction of key intake and discharge infrastructure, including temporary cofferdams, cooling water intake pump stations, and twin pipelines (both onshore and offshore). 

Significant dredging and disposal operations (424,000m³) were conducted alongside the installation of pipelines up to 380 meters offshore. The project also includes the fabrication and installation of intake heads, manholes, diffusers, and a permanent beacon platform for marine navigation

Scope of works

breakwater construction

summary of main work volume

Project

Sub-Contract for Civil Offshore Work of Combined Cycle Power Generating Facility of Up to 1200MW

project owner

Worldwide Holdings Berhad

Client

Pulau Indah Power Plant Sdn Bhd

Main Contractor

PEC Powercon Sdn Bhd

Focus

Marine Structures

Location

Pulau Indah, Selangor

contract period

1 October 2021 -
29 March 2024

contract sum

RM 46,724,989.96

related
projects

Discover the breadth of our expertise through our diverse range of projects and joint ventures

tanjung bin submarine pipeline
pekan submarine pipeline
setiu submarine pipeline